240 ton / day
Montaza – Alexandria – Egypt
March 2004 – Spt. 2004
ENTAG had signed a contract with Onyx Alexandria for supplying & constructing a complete sorting unit as a turnkey project. To serve as upgrading unit for the existing MSW sorting and composting plant.
ENTAG is providing the following services: Process design , site and topographical surveys ; geotechnical investigations ;detailed design and engineering for all civil, electrical works and mechanical equipment. Supply of equipment. Construction, Erection ; Commissioning and Start – up services.
The project complete at August 2004 by then the plant will be able to receive 400 ton/day of MSW instead of current capacity which is 160 ton/day.