Projects
Design and build municipal solid waste recycling and treatment plant

Lagos State Government- Nigeria
900ton / day.
November 2011
Engineering Capabilities

ENTAG had signed a contract combination withKonsadem Associates LTD Company forLagos state government for supplying & constructing a complete sorting unit as a turnkey project (design phase).

ENTAG is providing the following services:

  • Site survey.
  • Soil investigation.
  • Assess utility site requirements.
  • Develop design criteria.
  • Develop site master plan.
  • Prepare preliminary design report.
  • Prepare calculation sheets for all project components.
  • Preparing drawings and technical specifications for buildings road and infrastructure, MRF, composting facility and balefill (Epe Site).
  • Prepare bill of engineering measurements and initial cost estimates.

Prepare implementation time schedule

 

 

Copyrights © 2024 All Rights Reserved by ENTAG
Designed and developed by Spark Systems