Projects
Design Manufacture ,Supply,erection and construction of MSW sorting ,recycling and composting plant

Kossyah (Asuit Governorate ) - Egypt
Ton/day160
Oct. 2011 – Oct.2014

The Ministry of local development, through its technical sector, signed an agreement with the construction of MSW sorting ,recycling and composting plant ofKossyah plant, to serve the Governorate capital. ENTAG has signed a contracts with the ( Ministry of Military Production ) to serve as an engineering contractor for phase 5.

ENTAG provided the following services: Process design ,site and topographical surveys;geotechnical investigations; detailed design and engineering for all civil, architectural, electrical works and mechanical equipment. Supply of imported equipment. Construction management, supervision; testing , commissioning and start-up services.