Design and construction of MSW Sorting &composting plant ( Turnkey project ).

500 ton / day
Kota Kinabalu – Saba – Malaysia
March 2005 – march 2006 ( 12 monthes )
Engineering Capabilities

ENTAG had signed a contract with  Ms Smart Recycling ( Malysia ) for supplying & erection complete sorting & composting plant Saba Area as a turnkey project .

ENTAG is providing the following services: Process design , site and topographical surveys;detailed design and engineering for all civil, architectural , electrical works and mechanical equipment. Supply of equipment. Construction,erection; commissioning, The project is under construction.

The project main items are:

1.  One reception and sorting building including three sorting lines.

2.  Composting area with compost turning machines and water addition trucks.

3.  Design of steel & building of compost refining area.

Decomentation engineering, training and spare parts